Sunshine Project

In April 2019, Springfield voters approved Proposition S which enables Springfield Public Schools to make facility improvements to a number of schools, including renovating and expanding Sunshine Elementary School. SPS investing $13.89 million into Sunshine Elementary will:

  • Address accessibility and security challenges.
  • Add a safe room gymnasium.
  • Allow up to 350 to be served at the Sunshine site.

 

Sunshine progress as promised sign.
Sunshine Timeline
Sunshine Siste Aerial View
Sunshine Overview
Sunshine  View From Jefferson Ave.
Sunshine Construction Aerial Drawing
Sunshine East Entry - Parent Loop
Sunshine Floorplan
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Groundbreaking Aug. 29, 2019
Sunshine west parking lot construction
Oct. 2019
Sunshine construction
Nov. 2019
Sunshine construction
Dec. 2019
Sunshine construction
Jan. 2020

Construction

The estimated timeline for construction is to begin August 2019 with completion expected by August 2020.

  • The new construction for the expansion of Sunshine Elementary will occur while students are onsite in the current building. 
  • Renovation of the current Sunshine facility will be scheduled during student breaks (spring, winter, and summer breaks) to minimize disruption to learning. 

 

General Information

Work on the construction and renovation of Sunshine has been delayed and will not be completed prior to school beginning in August.  To provide the best possible learning environment while construction continues, school will begin on August 24 at the former Portland Elementary building, 906 W. Portland St. Learn more.


Beginning Sept. 3, 2019, the north driveway will be the only entrance and exit for traffic into and out of the parking lot.  This traffic pattern will last approximately four weeks.  

  • Only one driveway will be used to enter and exit the parking lot.  Be willing to take turns.
  • Expect delays.
  • Buses will be in the same traffic line.  Please allow them space to make wide turns in and out of the parking lot.

On August 29, 2019 at 10 a.m., a groundbreaking ceremony was held at Sunshine Elementary celebrating the renovation and expansion of the facility.


Information concerning impact to pick-up and drop-off procedures, due to the construction, will be shared before the beginning of the 2019-2020 school year.


The Sunshine attendance boundary will be adjusted, upon completion of construction, resulting in:

  • Moving entire Portland Elementary population to Sunshine location (effective 2020-2021 school year).
  • Moving 80-100 current Sunshine students to the new Delaware facility (effective 2020-2021 school year.

 

News and Information

Deduct for unused allowances

June 7, 2022

During its study session, the Board of Education approved the following:


Transom window, fire alarm, electrical wire mold change and handrails

November 2, 2021

During its regular meeting, the Board of Education approved the following:


Crossover ladder, floor repair, removal of magnetic hold opens, vinyl glass graphic, window shades, receptacles

August 17, 2021

During its combined meeting, the Board of Education approved the following:


Deduct for removal of annunciator & microphone from project

July 13, 2021

During its combined meeting, the Board of Education approved the following:


Deducts for doors & hardware and add emergency door shutoff

Jun. 8, 2021

During its study session, the Board of Education approved the following:


Electrical, tree removal and utility connection

Apr. 13, 2021

During its combined meeting, the Board of Education approved the following:


Additional Electric and Deducts for Sidewalk, Audio Devices, Playground, and Delays

Mar. 23, 2021

During its combined meeting, the Board of Education approved the following:


Second phase advances with contract approval

Feb. 9, 2021

During its combined meeting, the Board of Education approved:


Wiring, tamper switches, tile, new graphics

Jan. 19, 2021

During its combined meeting, the Board of Education approved:


Electrical adds and FF&E 

Nov. 17, 2020 

During its combined meeting, the Board of Education approved:


Painting base and trim, hold-open doors, and fire alarm strobes

Oct. 22, 2020 

During its study session, the Board of Education approved:


Plantings on campus, access control on exterior doors, and data and electrical adjustments around marker boards

Oct. 6, 2020 

During its study session, the Board of Education approved:


Additional inspections and cable work agreements/change orders

Sept. 22  2020

During its meeting, the Board of Education approved the following related to Sunshine bond project.


Agreement and change orders for Sunshine project 

Sept. 8  2020

During its meeting, the Board of Education approved the following related to Sunshine bond project.


FF&E for nurse's room 

Aug. 28  2020

During its meeting, the Board of Education approved the following related to Sunshine bond project.


Restroom re-piping and FF&E

July 30 2020

During its meeting, the Board of Education approved the following related to Sunshine bond project.


Electrical, drywall, hardware, cabinetry, and more

July 14 2020

During its meeting, the Board of Education approved the following related to Sunshine bond project.


Ceiling in cafeteria, wall patching, restroom re-piping, screen wall

June 23 2020

During its meeting, the Board of Education approved the following related to Sunshine bond project.


Wheels for bleachers, intercom speaker, framing and drywall, and other change orders approved

June 9, 2020

During its  meeting, the Board of Education approved the following related to Sunshine bond project.


Change orders HVAC and asbestos removal

During its combined meeting, the Board of Education approved the following related to Sunshine bond project.


Change orders for technology licensing and security cameras

Apr. 21, 2020

During its regular meeting, the Board of Education approved the following related to Sunshine bond project.


Multiple change orders approved

Apr. 14, 2020

During its study session , the Board of Education took action on the following items related to Sunshine bond project.


Furniture, Fixtures and Equipment approved

Mar. 10, 2020

During its study session , the Board of Education took action on the following items related to Sunshine bond project.


Sunshine attendance area boundary changes 

Feb. 6, 2020

Beginning with the 2020-2021 school year, the Sunshine attendance area will change. Learn more here.


Change orders and purchases

Feb. 4, 2020

The Board of Education approved two change orders and audiovisual equipment.


Change order for temporary fence, storm shelter items, removal of additional trees

Jan. 22, 2020

The Board of Education approved a change order for temporary commercial chain link fence for playground, ICC500 storm shelter items not included in original bid specs, and removal of two additional trees.


Change order for removal of soils and adding borrow material and base rock, credit for unused lean concrete and remaining allowances, verification of payment, curb and gutter constructed in phase 1

Dec. 10, 2019

The Board of Education approved change orders.


Change order for ground work and dimension plan revisions

Nov. 19, 2019

The Board of Education approved a change order for site, grading, private paving, sidewalk and dimension plan revisions.


Tree removal, top soil and ADA ramps change orders

Oct. 15, 2019

During its regular meeting, the Board of Education approved two change orders for Sunshine project.


Relocation of playground equipment

Oct. 1, 2019

During its regular meeting, the Board of Education selected Ozark Mountain Installations to relocate some of the playground.


Contract awarded for Sunshine project

Aug. 20, 2019

The Springfield school board approved a contract for renovation and construction related to the Sunshine Elementary School project during its Aug. 20 meeting. Bids were received from five contractors. The contract was awarded to Carson-Mitchell Inc., which was the lowest bidder at $11,089,600, slightly less than the original construction cost estimate of $11,571,000.

Additional action by the Board included:

  • Materials testing and special inspections for Delaware and Sunshine - Palmerton & Parrish

Approval for work for Sunshine project

June 25, 2019

During its monthly regular meeting, the Board of Education approved the following: