Storm Shelter Gymnasiums 2019

Tornado Safe Rooms/Gymnasiums

In April 2019, Springfield voters approved Proposition S which enables Springfield Public Schools to make facility improvements to a number of schools.  During the November 17, 2020 Board of Education meeting, it was reported that additional funds were available to address projects not included in the April 2019 bond.  The Board agreed to moving forward with phase two of the Hillcrest project, the construction of a new York Elementary, and the construction of tornado safe rooms/gymnasiums at Mann, Wilder, Field and Twain elementary schools.  


 

Choral Risers for stage at Field

March 28, 2023

During its combined meeting, the Board of Education received the following:


Change orders/agreements for Twain and Field include stormwater inlet, treated plywood and submittal exchange

December 13, 2022

During its combined meeting, the Board of Education approved the following:


Field (cameras/licenses, seed, sod, and awning) Twain (cameras/licenses, sod, chain link gate, asphalt paving and striping)

November 29, 2022

During its combined meeting, the Board of Education approved the following:


Field - door access controls, cameras, and removal/replacement of asphalt

October 11, 2022

During its study session, the Board of Education approved the following:


Field (asphalt, projector power/controls, yard hydrant, and vinyl numbers to existing doors - Twain (painting, camera rough-ins, vinyl numbers to existing doors, and fire department connection sign

September 27, 2022

During its regular meeting, the Board of Education approved the following:


Field (music classroom furniture, greenhouse, block flooring, concrete) Twain (music classroom furniture, wall phone device, block flooring)

August 16, 2022

During its combined meeting, the Board of Education approved the following:


Field (regrading playground and receptacle removal) Twain (tile and electrical line connection)

June 21, 2022

During its regular meeting, the Board of Education approved the following:


Field (Unsuitable soil and rock allowances and sewer line) Twain (Sewer adjustments, relocation of fire department connection)

May 17, 2022

During its combined meeting, the Board of Education approved the following:


Field (gas/water service, FF&E-audio visual equipment and A&E testing and balancing services) Twain (FF&E-audio visual equipment)

March 22, 2022

During its combined meeting, the Board of Education approved the following:


FF&E - physical education equipment at Field/Twain

February 15, 2022

During its combined meeting, the Board of Education approved the following:


FF&E - physical education equipment and tree removal at Field/Twain

January 18, 2022

During its combined meeting, the Board of Education approved the following:


Utility code requirements, testing and balancing credit, underground fiber optic routing, drywall expansion joints, tree removal at Field/Twain

Dec. 7, 2021

During its combined meeting, the Board of Education approved:


IT switches for Twain and Field and access points and playground equipment removal/reinstallation for Field

October 5, 2021

During its study session, the Board of Education approved the following:


Project management software for Field

August 17, 2021

During its combined meeting, the Board of Education approved the following:


Mann and Wilder MEP engineering & architectural services

August 17, 2021

During its combined meeting, the Board of Education approved the following:


Project management software for Field and Twain

August 17, 2021

During its combined meeting, the Board of Education approved the following:


Bids for Field and Twain storm shelter/gymnasium

June 8, 2021

During its combined meeting, the Board of Education approved the following:


Field, Mann and Twain testing and balancing services

May 18, 2021

During its combined meeting, the Board of Education approved the following:


Mann and Wilder commissioning services

Apr. 27, 2021

During its regular meeting, the Board of Education approved the following:

News and Information

Geotechnical Engineering & Commissioning Services for Field, Mann, Twain, Wilder

Mar. 23, 2021

During its combined meeting, the Board of Education approved the following:


Civil engineering, land surveying services, and geotechnical engineering services approved

Jan. 19, 2021

During its combined meeting, the Board of Education approved:


Architectural services approved for Mann, Wilder, Field and Twain storm shelter gymnasiums

Dec. 8, 2020 

During its combined meeting,  the Board of Education approved: