Boyd Project

In April 2019, Springfield voters approved Proposition S which enables Springfield Public Schools to make facility improvements to a number of schools, including building a new Boyd Elementary School. SPS will invest $20.34 million to build this new school, which will serve 300 pre-kindergarten to fifth-grade students. New construction will:

  • Address accessibility and security challenges
  • Provide a safe room gymnasium
  • Serve up to 300 pre- K-5 students
  • Serve as a regional early childhood mini-hub
Boyd Timeline
SW corner from Division St.
SE Corner from Division
Aerial View
Drawing

News and Information

FF&E - Additional library shelving

August 16, 2022

During its combined meeting, the Board of Education approved the following:


FF&E - Furniture for community room and administrative areas

January 18, 2022

During its combined meeting, the Board of Education approved the following:


Deduct for unused allowances and classroom furnishings

November 16, 2021

During its regular meeting, the Board of Education approved the following:


Nutrition Services Smallwares

October 5, 2021

During its study session, the Board of Education approved the following:


Design services and nutrition services smallwares

September 14, 2021

During its regular meeting, the Board of Education approved the following:


Fencing, circuiting for bleachers, window film and classroom shelving included in change orders

September 7, 2021

During its study session, the Board of Education approved the following:


Custodial equipment, landscaping, fiber connection and testing and balancing services

August 17, 2021

During its combined meeting, the Board of Education approved the following:


Security cameras and classroom furniture

July 13, 2021

During its combined meeting, the Board of Education approved the following:


PE equipment, removal of water treatment system, clocks & speakers, civil revisions, playground work

June 22, 2021

During its regular meeting, the Board of Education approved the following:


FF&E - Office Furniture

Jun. 8, 2021

During its study session, the Board of Education approved the following:


Office furniture, printers, EC classroom furniture

May 18, 2021

During its combined meeting, the Board of Education approved the following:


Phone system and network/wireless equipment

Apr. 27, 2021

During its regular meeting, the Board of Education approved the following:


FF&E addition

Apr. 13, 2021

During its study session, the Board of Education approved the following:


IT Equipment

Mar. 23, 2021

During its combined meeting, the Board of Education approved the following:


Change orders include ADA compliance and wall tile

Feb. 9, 2021

During its combined meeting, the Board of Education approved:


Work moves forward at Boyd

Jan. 19, 2021

During its combined meeting, the Board of Education approved:


Classroom furnishings

Dec. 8, 2020 

During its combined meeting, the Board of Education approved:


Corner guard change, millwork adjustment, removal of stage curtain liner, and solid surface counter

Oct. 22, 2020 

During its study session, the Board of Education approved:


Change orders for BP Builders

Sept. 8 2020

During its meeting, the Board of Education approved the following related to Boyd bond project.


Locate and cap sewer line

July 14 2020

During its meeting, the Board of Education approved the following related to Boyd bond project.


Change orders needed for special inspections and materials testing services and alley vacation

June 9, 2020

During its meeting, the Board of Education approved the following related to Boyd bond project.


Construction bid approved

May 19, 2020

During its combined meeting, the Board of Education took action on the following items related to Boyd bond project.


Engineering services approved

Apr. 14, 2020

During its study session , the Board of Education took action on the following items related to Boyd bond project.


Easement and commissioning service approvals

Mar. 10, 2020

During its study session , the Board of Education took action on the following items related to Boyd bond project.


Change orders for civil engineering

Feb. 4, 2020

During its study session, the Board of education approved additional civil engineering work needed for transportation and storm water public improvements.

Change orders and utility easement approved

Jan. 21, 2020

During its combined meeting, the Board of Education approved:


Change orders and utility easement approved

Dec. 10, 2019

During its combined meeting, the Board of Education approved:


Demolition contract awarded for site of future Boyd Elementary

Oct. 15, 2019

During its regular meeting, the Board of Education approved the demolition contract for Berry and adjacent properties that will become the site for the new Boyd Elementary School.


Contract awarded for graphics

Oct. 1, 2019

During its regular meeting, the Board of Education approved the environmental graphics contract for Boyd Elementary to Hollis+Miller.


Asbestos abatement at Berry site and property purchased for new Boyd

Aug. 20, 2019

The Springfield school board approved a contract for asbestos abatement at Berry site and property purchased for new Boyd.


Kitchen design services awarded

July 24, 2019

During a special meeting, the Board of Education awarded Fellers Food Service Equipment a contract for kitchen design services for the new Boyd Elementary School.


Board approves engineering fees for Boyd

June 4, 2019